ACTIVITIES
|
PROGRAMMES
|
OBJECTIVES
|
TARGETS
|
MEASURES TAKEN
|
MEASURES PLANNED
|
TIMESCALES
|
RESPONSIBILITIES
|
Storage of oils, paints and chemicals in bunded areas
|
Bund integrity
|
Prevent any oil/chemical/paint spills seeping through the bunds
|
Ensure bunds are impervious to hazardous substances by Dec 1998
|
None
|
Apply a suitable impervious coating to bunds
|
to be agreed
|
to be agreed
|
Check integrity of interceptor by Dec 1998
|
to be agreed
|
to be agreed
|
Emergency notices
|
Prevent any oil/chemical spills entering the drainage system
|
Ensure personnel know not to allow hazardous substances to enter the drainage system by Oct 1998
|
Emergency spill procedure available
|
Put up emergency spill notices at appropriate locations and train emergency response team
|
to be agreed
|
to be agreed
|
Use of electricity and gas for production and heating
|
Energy efficiency
|
Minimise electricity consumption where practical
|
Reduce electrical consumption by 5% of present levels within 12 months
|
Energy management system in place. Monthly monitoring of bills.
|
Use portable metering equipment to measure electricity and gas consumed by individual machines and/or departments to target areas of wastage
|
to be agreed
|
to be agreed
|
Undertake a survey of the compressed air system and investigate methods of increasing efficiency
|
to be agreed
|
to be agreed
|
Encourage personnel to save energy by raising awareness of energy issues
|
to be agreed
|
to be agreed
|
ACTIVITIES
|
PROGRAMMES
|
OBJECTIVES
|
TARGETS
|
MEASURES TAKEN
|
MEASURES PLANNED
|
TIMESCALES
|
RESPONSIBILITIES
|
Compressors
|
Water contamination
|
Prevent hazardous substances entering controlled waters
|
Ensure blowdown from compressor does not discharge onto made up ground by Nov 1998
|
None
|
Repair compressor and clean up affected ground appropriately
|
to be agreed
|
to be agreed
|
Implement measures to remove oil from water discharged from outfall pit by Feb 1998
|
Clean out the outfall pit annually
|
Investigate and recommend method(s) for removing oil contamination
|
to be agreed
|
to be agreed
|
Electro-deposition and spray painting of finished goods
|
Solvent use
|
Determine how much solvent is lost/extracted to atmosphere where possible
|
Monitor solvent vapour loss by Feb 1998
|
None
|
Set up spreadsheet to monitor solvent consumption and waste and calculate vapour losses
|
to be agreed
|
to be agreed
|