Chart Plotting Exercise (10)

The next module, A4 was one of the three to be completed on 27th August. It was estimated that this module would take 15.0 hours to develop; in fact it took 22.5 hours.

Module A6 A5 C2 A4        
Date Completed 20/8 21/8 23/8 27/8        
Actual 33.0 37.5 48.0 22.5        
Estimated 37.5 30.0 37.5 15.0        
X -4.5 7.5 10.5          
mR   12.0 3.0          

Using the information in the table above, calculate the values of X and mR that will be used to complete the rest of the column.

X =

mR =