Chart Plotting Exercise (7)

The third module to be completed is module C2, which is finished on August 23rd. It was estimated that this module would take 37.5 hours to produce, but it actually took 48 hours.

Module A6 A5 C2          
Date Completed 20/8 21/8 23/8          
Actual 33.0 37.5 48.0          
Estimated 37.5 30.0 37.5          
X -4.5 7.5            
mR   12.0            

What is the value of X for this module?

X =